Payment for construction
Contents |
[edit] Introduction
In general terms, 'payment' is the transfer between parties of some form of value (such as funds, services, assets) in an agreed exchange. This can be for goods, services or to fulfil a legal obligation such as a debt. The most common form of payment involves money although it can also take the form of stock issues or other benefits, and is typically preceded by a bill or invoice specifying the amount due.
The payee (the party being paid) generally has the right to specify the method of payment they will accept from the payer (the party that is paying). The payee may decide that they will accept a part/discounted payment in exchange for certain conditions, i.e. a cash payment, prompt payment, and so on.
By accepting a payment, the payee extinguishes the debt or other obligation that was owed to them by the payer, and usually acknowledges the payment by issuing a receipt. Generally a payee cannot unreasonably refuse acceptance of a payment.
[edit] Construction industry
In the construction industry, payment can be the source of a great deal of controversy. Not only are the sums involved very large, and the duration of projects very long, but the total amount payable tends to change over time. In addition, contractors, subcontractors and suppliers face considerable risk when pricing construction projects, and optimistic pricing or late payments can quickly cause cash flow problems.
As a result, payments are often be the source of disputes which can ultimately lead to a breakdown in relationships and even project or business failure.
[edit] Agreeing the price
Prices are typically agreed by a tender process, during which the client issues details of the works required, and prospective suppliers submit prices and other information for consideration.
See Tender process for more information.
The price agreed for construction works is often referred to as the ‘contract sum’. However, this sum is rarely ‘fixed’, and contracts will typically allow the price to change under certain circumstances:
- Variations: Most contracts will contain provision for the architect or contract administrator to issue instructions to vary the design, quantities, quality, sequence or working conditions.
- Relevant events: A relevant event may be caused by the client (for example failure to supply goods or instructions), or may be a neutral event (such as exceptionally adverse weather) and may result in a claim for loss and expense by the contractor.
- Provisional sums: These are allowances for a specific element of the works that is not defined in enough detail for tenderers to price.
- Fluctuations: A mechanism for dealing with inflation on projects.
- Payments to nominated sub-contractors or nominated suppliers.
- Statutory fees.
- Payments relating to opening-up and testing the works.
Depending on the nature of the contract therefore, prices may be referred to as; fixed, firm, guaranteed maximum price, target cost, lump sum, measurement, open book, and so on.
[edit] Payment process
The Housing Grants, Construction and Regeneration Act includes provisions to ensure that payments are made regularly and promptly throughout the supply chain. Interestingly, the Act does not stipulate payment periods, simply providing that parties are free to agree what payments are due and when, i.e. the contract must set out an adequate mechanism for determining these matters. If contracts do not comply with the Act, the Scheme for Construction Contracts applies.
Typically, regular payments are allowed for by interim certificates, generally valued by the cost consultant. The client must honour interim certificates within the period stipulated by the contract.
See Interim certificates for more information.
[edit] Retention
Retention is a percentage (often 5%) of the amount certified as due to the contractor on an interim certificate, that is deducted from the amount due and retained by the client. The purpose of retention is to ensure that the contractor properly completes the activities required of them under the contract.
Half of the amount retained is released on certification of practical completion, and the remainder is released upon certification of making good defects.
See Retention for more information.
[edit] Fair payment practices
Construction 2025, the government's long-term vision for the future of the construction industry, cited equitable financial arrangements and certainty of payment as critical success factors for the industry and proposed a need to ‘...create conditions for construction supply chains to thrive by addressing access to finance and payment practices.’
Measures undertaken to try to ensure fair payment have included:
- The Housing Grants, Construction and Regeneration Act.
- The Late Payment of Commercial Debts (Interest) Act.
- The Late Payment of Commercial Debts Regulations.
- Construction Supply Chain Payment Charter.
- Small Business, Enterprise and Employment Act.
- Project bank accounts.
- Prompt payment code.
- Retention held in trust fund.
See Fair payment practices for more information.
[edit] Related articles on Designing Buildings
- Barter.
- Causes of construction disputes.
- Construction invoice fraud.
- Construction supply chain payment charter.
- Fair payment practices.
- Housing Grants, Construction and Regeneration Act.
- The Late Payment of Commercial Debts Regulations 2013.
- Payment notice.
- Payments to nominated sub-contractors.
- Pay less notice.
- Payment holiday.
- Payment schedule.
- Project bank accounts.
- Prompt payment code.
- Scheme for construction contracts.
- Small Business, Enterprise and Employment Bill.
- The causes of late payment in construction.
Featured articles and news
The continued ISG fall out, where to go?
Support for ISG contractors, companies and employees.
New HES national centre for traditional building retrofit
Announced as HES publishes survey results which reveal strong support for retrofit.
Retrofit of Buildings, a CIOB Technical Publication
Expected to become one of the largest activities in the global construction industry.
The ECA industry focus video channel
Keeping update with the industry session by session.
Over 25 recorded informations sessions freely available.
AT Awards 2024 ceremony East London October 25th.
Revisiting the AT community at the 2023 awards evening.
The Community Housing Fund and built affordable homes
CLTN reviews the impact of the Fund and calls for extension.
The grading system of the Regulator for Social Housing
A background, an explanation and ten recent enforcements.
Construction, repair and maintenance. Book review.
Putting new life into a city with a 1900 year history.
BSRIA Briefing 2024: Sustainable Futures speakers
Redefining Retrofit for Net Zero Living 22 Nov.
Wall of support for post-Grenfell regulation of electricians
Call for a shake-up of the construction industry highlighted on radio.
Digital sustainability through future AEC tools
Bringing together industry and academia to meet challenges.
Skills gap for net zero highlighted to Minister for Industry
ECA convenes roundtable discussion at Portcullis House.
Evidencing Net Zero with the new UK buildings standard
Pilot version with detailed excel proforma out now!
Scottish Building Safety Levy, in consultation
From direct remediation and the RPDT, to the costs and alternatives.
Waves of warmer homes grants for the rental sector
Boosting energy efficiency standards for all rented homes.
A refocus of the National Planning Policy Framework
Key terms described in brief, as the consultation closes the evening of the 24th.
Fortified farmhouses of the unruly 16th-and 17th-century borders.